Abstract

Ultimately, the team decided to reconfigure the double-circuited, vertically configured towers to a double-circuit, deltatype configuration. The team devised a plan to reconfigure the circuits so that the top phase wire on each side along with one of the middle phase wires would comprise one circuit rather than having a circuit on each side of crossings towers. [Extracted from the article]

Additional Information

  • Source:Transmission & Distribution World. 2023/10, p14
  • Document Type:Article
  • Subject Area:Power and Energy
  • Publication Date:2023
  • ISSN:1087-0849
  • Accession Number:173388957
  • Copyright Statement:Copyright of Transmission & Distribution World is the property of Endeavor Business Media and its content may not be copied or emailed to multiple sites without the copyright holder's express written permission. Additionally, content may not be used with any artificial intelligence tools or machine learning technologies. However, users may print, download, or email articles for individual use. This abstract may be abridged. No warranty is given about the accuracy of the copy. Users should refer to the original published version of the material for the full abstract. (Copyright applies to all Abstracts.)

Looking to go deeper into this topic? Look for more articles on EBSCOhost.